ORSTED- Windfarm Construction Activity
September 1 - November 6
Scope: Nearshore Export Cable Installation
Type of Work:
Pre-lay Grapnel Run, Boulder Clearance, Pre-lay Survey, Post-lay survey, Exit pit pull in, Cable Installation, Cable Crossings
Vessel(s): Barge and Tugs, Shelia Bordelon
Notes: Anchor spread, boulder Grab